Close
DOMOTEX asia/CHINAFLOOR 2026
Friday, April 17, 2026
R+T Asia 2026

Sarens Lifting Beams on Iconic Al Hadarat Bridge Project in Cairo

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Related stories

7 Mistakes to Avoid When Managing Security on Your Jobsite

Construction sites are common targets for criminals. They contain...

Gammon Deploys Low-Carbon Concrete in Hong Kong Project

A sustainability-focused construction approach is being implemented in Hong...

What Are the Top-Rated Heavy Equipment Rental Companies? These 5 Are Currently Leading in the U.S.

In construction and similar sectors, renting heavy equipment can...
- Advertisement -

Sarens is proud to have helped construct what will be one of the highest bridges in Africa, the Al Hadarat Bridge in Cairo. Over the course of several weeks, Sarens completed two triumphant lifting operations on behalf of Arab Contractors, bringing the bridge project closer to completion.

Sarens first lifted and installed eleven 150t, 41m steel beams. For this, the crew used a CC4800 crane in SSL configuration and 66m main boom, as well as 270t SL CW. After taking each beam from its initial location, they would slew the crane into position. The four-member crew successfully performed 11 picks over the course of one week.

Sarens is proud to have helped construct what will be one of the highest bridges in Africa, the Al Hadarat Bridge in Cairo. Over the course of several weeks, Sarens completed two triumphant lifting operations on behalf of Arab Contractors, bringing the bridge project closer to completion.

Sarens first lifted and installed eleven 150t, 41m steel beams. For this, the crew used a CC4800 crane in SSL configuration and 66m main boom, as well as 270t SL CW. After taking each beam from its initial location, they would slew the crane into position. The four-member crew successfully performed 11 picks over the course of one week.

Achema Middleeast

Latest stories

Related stories

7 Mistakes to Avoid When Managing Security on Your Jobsite

Construction sites are common targets for criminals. They contain...

Gammon Deploys Low-Carbon Concrete in Hong Kong Project

A sustainability-focused construction approach is being implemented in Hong...

What Are the Top-Rated Heavy Equipment Rental Companies? These 5 Are Currently Leading in the U.S.

In construction and similar sectors, renting heavy equipment can...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Translate »